Friday, October 15, 2021

A great day in the Village

›
The Doppelmayr crew is placing all of the towers and bull wheels for the new Cannon Valley Quad chairlift today.  Today was almost as exciti...
Tuesday, October 12, 2021

Doppelmayer crew is here

›
The lift building crew from Doppelmayer has been on site now for a few days and they hard at work building the new Cannon Valley Quad Chairl...
Thursday, September 30, 2021

Towers & Rope!

›
The towers for the new Cannon Valley Quad chairlift arrived first thing this morning. The haul rope for the lift arrived earlier this week. ...
Friday, August 20, 2021

The final pour

›
The last big concrete pour in the construction of the new Cannon Valley Quad chairlift happened today as two trucks filled the bottom column...
Tuesday, August 3, 2021

Pouring the bottom terminal footings

›
A lot of ready mix was poured today thanks to our friends at Four Corners in Hastings, MN. Close to 30 yards from three trucks to be exact a...
Tuesday, July 20, 2021

Right on schedule

›
More pouring, more footings, and a lot of progress happening with our big summer new chairlift project. There are just a couple of tower foo...
Tuesday, July 6, 2021

New chairlift footings

›
Our team has been hard at work in June and now July with the new chairlift footings. The footing for the top terminal of the lift is now com...
2 comments:
‹
›
Home
View web version

About Me

My photo
Peter Zotalis
Peter Zotalis is the President/General Manager at Welch Village Ski and Snowboard Area in Welch, MN.
View my complete profile
Powered by Blogger.