Tuesday, August 3, 2021

Pouring the bottom terminal footings

A lot of ready mix was poured today thanks to our friends at Four Corners in Hastings, MN. Close to 30 yards from three trucks to be exact as we poured one of the footings for the bottom terminal area of the new chairlift. 

We are still in schedule with the new lift project. There will be one more additional pour for the bottom terminal area and the two pours for two more towers. That will conclude a huge phase of this project. 