Tuesday, December 14, 2021

Cannon Valley Quad Load Test

Our team helped the Doppelmayr team complete a successful load test yesterday for our new chairlift. This is one of the most important items to check of the "New Chairlift To Do" list.

In these photos you will see big boxed containers that were filled with water in order to simulate the chairlift being fully loaded with skiers and snowboarders. 
  
Doppelmayr will be performing some additional final tests this week. Still not quite sure when the lift will open, stay tuned, that day is coming very, very soon. 