Thursday, September 30, 2021

Towers & Rope!

The towers for the new Cannon Valley Quad chairlift arrived first thing this morning. The haul rope for the lift arrived earlier this week. And…we have received word that the crew from Doppelmayer that will build the rest of the lift will arrive late next week. Once that crew begins their work, this project will really begin to ramp up. Stay tuned for a more steady diet of new lift updates through the month of October! 







Friday, August 20, 2021

The final pour

The last big concrete pour in the construction of the new Cannon Valley Quad chairlift happened today as two trucks filled the bottom column of the bottom terminal with a two trucks and a pump. On top of this column will sit the bull wheel and bottom gantry of the new chairlift.  Pretty soon now, we’ll turn over the majority of the remaining work on the lift construction to the Doppelmayer crew. Really exciting to see this new quad chairlift take shape on the east side of the Village!







Tuesday, August 3, 2021

Pouring the bottom terminal footings

A lot of ready mix was poured today thanks to our friends at Four Corners in Hastings, MN. Close to 30 yards from three trucks to be exact as we poured one of the footings for the bottom terminal area of the new chairlift. 

We are still in schedule with the new lift project. There will be one more additional pour for the bottom terminal area and the two pours for two more towers. That will conclude a huge phase of this project. 









Tuesday, July 20, 2021

Right on schedule

More pouring, more footings, and a lot of progress happening with our big summer new chairlift project. There are just a couple of tower footings left to pour and the bottom terminal footing. Our crew is right on schedule with this huge project and I can’t wait to see the finished product. 






Tuesday, July 6, 2021

New chairlift footings

Our team has been hard at work in June and now July with the new chairlift footings. The footing for the top terminal of the lift is now completed and work is underway with tower footings. Below are some recent photos of the work. 

Top terminal completed footing 



Old lift towers, which will come down soon. New lift line just to the right! 


Rebar artwork or tower footings? 😎







Tuesday, June 8, 2021

New Chairlift Update: June 8

Our new quad chairlift installation project is in full swing. Today was an important day because most of the rebar for the tower and terminal footings arrived. Next, our team will begin assembling all of the rebar and get ready to pour the footings in the next couple weeks or so. We’ll keep you posted with more updates again soon. A lot will be happening now with this big project in the next few weeks and will continue all the way through the start of the 2021-22 season. 










Tuesday, May 11, 2021

We have some exciting news to share!
This spring, we contracted with Doppelmayr USA Inc to construct and install a brand new 4-person fixed grip chairlift on the east side of the ski area.  This new lift will replace the Hall #4 double chairlift and be constructed near the same lift line.  The bottom of the lift will actually be placed about 30 ft to the west (towards Jaxx).  You will unload the new lift in the same location as the #4 double chair.  

By moving the bottom of this new lift further to the west, we will be able to open up the bottom of the Harley's Hollow enabling guests to actually ski and ride in-between the new quad chair and the Triple Chair.  There are a lot of exciting aspects to this project (and other projects) that we will share with you over the course of the summer and fall.  

Right now, the anticipated opening for this lift is early December.  Our crew has begun to take down the double chair and we will also soon be taking down the Hall #3 double chair on Bakkelyka as well.  We have not used this lift for several seasons now primarily because we have two 4-person chairs that service the same area. 

This is new lift will look just like the pictures below.  The lift itself will be very similar to the two Doppelmayr quad lifts we currently have (Lookout #2 chair & Back Bowl #6 chair) but will have some added modern advances like a larger bottom terminal building.  

We are also expecting to finish work on the East and West Quad Riplet lifts and add restraining bars to those lifts this summer as well.   Superior Tramway has experienced significant manufacturing and shipping delays because of the pandemic.  

We are excited about adding yet another brand new, state of the art, chairlift to Welch Village.  Look for more updates on this project and more very soon!